Saudi Arabia Solar-Plus-Storage Step-Up Project — Project Case

Fengguang Transformer delivered a tailored power package — eight 15 MVA and four 10 MVA main transformers — for a 120 MW solar-plus-storage step-up project in Riyadh, Saudi Arabia. Explore how our engineering team solved real-world challenges in solar-plus-storage step-up project.

Power quality at a 120 MW solar-plus-storage step-up project in Riyadh came down to one question: could the distribution equipment hold up under real site conditions? Fengguang Transformer answered with eight 15 MVA and four 10 MVA main transformers — selected and engineered for this specific solar-plus-storage step-up project.

The Site

On site, the facility connects to a desert grid with high ambient heat and dust, and the local extreme desert heat exceeding 50 °C with heavy dust is a constant factor in equipment design. Saudi Arabia’s Middle East industrial growth has raised expectations for both capacity and continuity of supply.

Scope of Supply

Fengguang’s scope for a national renewable-energy developer covered eight 15 MVA and four 10 MVA main transformers, from selection and custom design through factory testing, shipment and installation supervision. Every unit was checked against the client’s actual load data before it left the factory.

The Engineering Challenge

Extreme heat and blowing dust pushed cooling systems hard, while the fluctuating output of PV and storage demanded flexible, robust step-up transformation. That was the practical problem our engineers had to solve — the kind of issue that a generic datasheet never reveals and that only shows up once a plant is running at full load.

Client Requirements

  • Operate at 50 °C+ ambient without derating.
  • Handle bidirectional power flow from storage.
  • Resist abrasive dust ingress.
  • Meet utility grid-code requirements.

Our Solution

The specification centered on SZ13 step-up transformers and ZGS combined substations. Three decisions shaped the final design:

Electrical performance. Optimized impedance for inverter compatibility and oltc for voltage control — a direct response to the loads measured on site.

Site resilience. The units were built with IP-rated enclosures, enhanced cooling and dust-resistant filters, so performance holds up despite the local environment.

Service and partnership. Detailed documentation, remote technical support and operator training were included, with spare parts kept readily available.

Results in Service

More than a year on, the numbers speak clearly: 24 months without a fault, 99.92% supply availability, about 260 GWh delivered annually and cut 150,000 t of CO₂ a year. For a national renewable-energy developer, that translated into steadier production and lower operating cost — the outcome the project was commissioned to achieve.

Key Takeaways

Every site is different, and this one demanded more than an off-the-shelf unit. By starting from the load study and working outward, Fengguang delivered a transformer package that fits Riyadh’s grid and climate. It is one more example of how our team turns a solar-plus-storage step-up project brief into dependable power — and a reference we can build on across Saudi Arabia.

FAQ

What was the key challenge in this Riyadh installation?

Extreme heat and blowing dust pushed cooling systems hard, while the fluctuating output of PV and storage demanded flexible, robust step-up transformation. We addressed it through targeted design choices rather than a standard catalog unit.

Which transformer series did Fengguang choose?

SZ13 step-up transformers and ZGS combined substations, tailored to the site’s load profile and environment.

How quickly can Fengguang support a comparable project?

Our engineers work from your load data and site conditions. Contact our team and we will outline a proposed design and schedule.