Fengguang Transformer delivered a tailored power package — ten 1,250 kVA and six 800 kVA units — for a 20 MW textile industrial zone in Dhaka, Bangladesh. Explore how our engineering team solved real-world challenges in textile industrial zone.
On site, the facility connects to an industrial network with frequent load shedding, and the local hot, humid monsoon climate is a constant factor in equipment design. Bangladesh’s South Asia industrial growth has raised expectations for both capacity and continuity of supply.
Fengguang’s scope for a textile manufacturers’ association covered ten 1,250 kVA and six 800 kVA units, from selection and custom design through factory testing, shipment and installation supervision. Every unit was checked against the client’s actual load data before it left the factory.
Frequent load shedding and voltage instability disrupted production, and many small units needed a standardized, easy-to-maintain solution. That was the practical problem our engineers had to solve — the kind of issue that a generic datasheet never reveals and that only shows up once a plant is running at full load.
The specification centered on S11 and S13 oil-immersed distribution transformers. Three decisions shaped the final design:
Electrical performance. Rugged, standardized design with good overload margin — a direct response to the loads measured on site.
Site resilience. The units were built with sealed tanks suited to humid conditions, so performance holds up despite the local environment.
Service and partnership. Detailed documentation, remote technical support and operator training were included, with spare parts kept readily available.
More than a year on, the numbers speak clearly: 18 months without a fault, 99.7% supply availability, about 40 million kWh delivered annually and cut 23,000 t of CO₂ a year. For a textile manufacturers’ association, that translated into steadier production and lower operating cost — the outcome the project was commissioned to achieve.
Every site is different, and this one demanded more than an off-the-shelf unit. By starting from the load study and working outward, Fengguang delivered a transformer package that fits Dhaka’s grid and climate. It is one more example of how our team turns a textile industrial zone brief into dependable power — and a reference we can build on across Bangladesh.
Frequent load shedding and voltage instability disrupted production, and many small units needed a standardized, easy-to-maintain solution. We addressed it through targeted design choices rather than a standard catalog unit.
S11 and S13 oil-immersed distribution transformers, tailored to the site’s load profile and environment.
Our engineers work from your load data and site conditions. Contact our team and we will outline a proposed design and schedule.
Contact our team to discuss your project requirements.